A resource is a person, group of people, or piece of equipment needed to accomplish a task.
MacProject II calculates resource duration based on the calendar assigned to that resource and on other information you provide when you allocate a resource to a task.
-- part contents for card part 2
----- text -----
Important: Resource duration is calculated according to the calendar in effect for the resource when it is allocated to that task. If you do not want the Project Calendar used for your resources, you should set and assign calendars before allocating resources to tasks.
MacProject II automatically uses the Project Calendar for resources. If you want to assign a different calendar for a resource, you should do that before you allocate the resource to tasks.